Technology Improvement Scheme and Verification of ±800  kV DC Thyristor Valve

HAO Changcheng1, WANG Huafeng1, YANG Wankai2, WANG Binze1, ZHOU Liang3   

  1. 1. State Grid Smart Grid Research Institute, Beijing 102209, China;2. China Electric Power Research Institute, Beijing 100192, China;3. China-Epri Electric Engineering Co. Ltd., Beijing 102200, China
  • Online:2016-02-01

Abstract:

The technical improvement project of pole Ⅱ lower converter valve in ± 800 kV HVDC
 Southern  Hami south converter station is the first technical improvement project of certain foreign brand HVDC valve completed in China. This paper firstly introduces the technical defects and technical promotion programs of this foreign brand valve, and then discusses the designs and main innovation points of project commission programs of subsystem, station system and whole system. Site test analysis results show that the running temperature of DC grading resistor of improved thyristor valve is significantly reduced, and thyristor state detection mechanism is improved. There is no protection misoperation, fault trip or commutation failure in the test, and the performance parameters of improved thyristor valve meet the requirements of engineering design.

Key words: high voltage direct current (HVDC), thyristor valve, type test, project commissioning