电力建设 ›› 2018, Vol. 39 ›› Issue (4): 45-.doi: 10.3969/j.issn.1000-7229.2018.04.007

• 储能技术 • 上一篇    下一篇

 电池储能参与配电网削峰填谷的变功率控制策略

 孟娅1 ,李欣然1 ,黎淑娟1 ,黄际元2

 
  

  1.  (1.湖南大学电气与信息工程学院,长沙市 410082;2.国网湖南省电力有限公司长沙供电分公司,长沙市 410015)
     
  • 出版日期:2018-04-01
  • 作者简介:孟娅(1990),女,博士研究生,主要研究方向为储能在电力系统中的应用; 李欣然(1957),男,教授,博士生导师,主要从事电力系统分析控制、负荷建模等方面的研究工作; 黄际元(1988),男,博士,工程师,主要从事新能源、储能在电力系统中的应用等方面的工作。
  • 基金资助:
     基金项目:国家重点研发计划项目(2017YFB0903504);湖南省科技重大专项(2016GK1003);国网湖南省电力有限公司科技项目(5216A1170002)

 Variable Power Control Strategy of Battery Energy Storage System Participating in Distribution Network Peak Load Shifting

 MENG Ya1, LI Xinran1 ,LI Shujuan1 ,HUANG Jiyuan2

 
  

  1.  (1.College of Electrical and Information Engineering, Hunan University, Changsha 410082, China;2.State Grid Hunan Electric Power Corporation Limited Changsha Power Supply Company, Changsha 410015, China)
     
  • Online:2018-04-01
  • Supported by:
     Project supported by  National Key Research and Development Program of China (2017YFB0903504)
     

摘要:  摘要:电力负荷的构成随着社会经济的发展变得复杂多样,并且随着新能源的并入,配电网中负荷峰谷差问题也愈加突出。储能系统具有快速响应、精确控制及能量双向流动的特点。在电力系统中配置储能是实现“削峰填谷”的一种有效方案。该文提出一种电池储能参与配电网削峰填谷的可变功率控制策略,以1天为时间尺度,以储能系统电量平衡为准则,有效改善了配电网峰谷差过大的问题。以某电网中变电站实际负荷数据为算例,基于相应评价指标,就所提可变功率策略与目前常用的恒功率策略进行对比试验,验证了所提方法的可行性和有效性。

 

关键词:  , 关键词:  , 电池储能, 削峰填谷, 控制策略, 配电网

Abstract:

ABSTRACT:   With the fast development of social economy, the composition of power load becomes more complicated, and the integration of new energy in the distribution network also makes the problem of load peak and valley worse. Battery energy storage system, with its characteristics of rapid response, precise control and energy bidirectional flow, becomes an effective program to achieve ‘cutting peak filling’ in power system. This paper proposes a variable power control strategy for battery energy storage involved in peak load shifting in distribution networks. This strategy takes one day as the time scale and the energy balance of the energy storage system as the criterion, which effectively improves the peak-problem of distribution network. Taking the actual load data of a power substation as an example, the effectiveness of the proposed method is verified by comparing the proposed variable power strategy with the commonly used constant power strategy based on the proposed evaluation index.
 

Key words:  KEYWORDS: battery energy storage, peak load shifting, control strategy, distribution network

中图分类号: