ELECTRIC POWER CONSTRUCTION ›› 2012, Vol. 33 ›› Issue (1): 46-49.

Previous Articles     Next Articles

Application of KTACSR/EST Conductor in Large-crossing Transmission Projects

  

  • Received:2011-11-01 Revised:2011-11-29 Online:2012-01-01 Published:2012-05-31
  • Contact: Chun-Ping PAN E-mail:xuli@gedi.com.cn

Abstract:

Conductor selection is an important link in designing large-crossing transmission project. In this paper, the characteristics of KTACSR/EST conductor and its application in large-crossing transmission projects are introduced. Taking a new-built large-crossing transmission project in Guangdong province as an example, the technical and economic comparison of different kinds of conductors are carried out. It is shown that the KTACSR/EST conductor can reduce the wind load of the tower and the investment of project effectively.