考虑蓄电池空间分布的协调控制策略

李秀磊,耿光飞

电力建设 ›› 2016, Vol. 37 ›› Issue (11) : 35.

PDF(1432 KB)
PDF(1432 KB)
电力建设 ›› 2016, Vol. 37 ›› Issue (11) : 35. DOI: 10.3969/j.issn.1000-7229.2016.11.006
储能技术

 考虑蓄电池空间分布的协调控制策略

  •  李秀磊,耿光飞
作者信息 +

Coordinated Control Strategy Considering Spatial Distribution of Storage Battery 

  •  LI Xiulei, GENG Guangfei
Author information +
文章历史 +

摘要

 随着配电网不断的复杂化以及主动配电网、智能电网等概念的提出,在配电网中将可能有多个储能系统存在,而当前对储能系统的运行研究主要集中在时间上的优化,很少有涉及其在空间上的优化。提出一种两阶段蓄电池储能系统(battery energy storage system,BESS)运行控制策略制定方法:一阶段以储能套利与削峰收益之和最大为目标,根据分时电价划分充放电时间段,将所有储能系统看作一个整体,在时间周期上制定总的运行控制策略;二阶段在一阶段基础上进行空间二次优化,考虑网络结构,以降低网损所得收益最大为目标,对各储能系统在各时间段上的充放电功率进行分配。最后以修改的IEEE 33节点系统作为算例,验证了本文所提方法的有效性。

Abstract

 With the continuous complexity of distribution network, and the concepts of active distribution network, smart grid, there may be a number of energy storage systems in distribution network. However, the current researches on the operation of energy storage system are mainly focused on the optimization of time, and there are few of them involved in the optimization of the space. This paper presents a method for the control strategy of the two-stage energy storage system operation: in the first stage, it is the goal of the maximum benefit of the energy storage arbitrage and peak clipping, divides the time period of charging and discharging according to time-of-use price, all the energy storage systems are considered as a whole, and the total operation control strategy is formulated in the time period; the second stage is the second optimization of the space on the basis of the first stage, taking into account the network structure, the objective function is the maximum of the benefit of saving energy, the charging and discharging power of each energy storage system in each time period are distributed. Finally, a modified IEEE 33 node system is used as an example to verify the effectiveness of the proposed method.
 

关键词

  / 配电网 / 空间分布 / 蓄电池储能系统(BESS) / 协调控制策略

Key words

 distribution network / spatial distribution / battery energy storage system(BESS) / corrdinated control strategy

引用本文

导出引用
李秀磊,耿光飞.  考虑蓄电池空间分布的协调控制策略[J]. 电力建设. 2016, 37(11): 35 https://doi.org/10.3969/j.issn.1000-7229.2016.11.006
LI Xiulei, GENG Guangfei. Coordinated Control Strategy Considering Spatial Distribution of Storage Battery [J]. Electric Power Construction. 2016, 37(11): 35 https://doi.org/10.3969/j.issn.1000-7229.2016.11.006
中图分类号:      TM 732   

参考文献

 [1]廖怀庆,刘东,黄玉辉,等.考虑新能源发电与储能装置接入的智能电网转供能力分析[J].中国电机工程学报,2012,32(16):9-16.
LIAO Huaiqing,LIU Dong,HUANG Yuhui,et al.Smart grid power transfer capability analysis considering integrated renewable energy resources and energy storage systems[J].Proceedings of the CSEE,2012,32(16):9-16.
[2]苏小林,李丹丹,阎晓霞,等.储能技术在电力系统中的应用分析[J].电力建设,2016,37(8):24-32.
SU Xiaolin,LI Dandan,YAN Xiaoxia,et al.Application analysis of energy storage technology in power system[J].Electric Power Construction, 2016,37(8):24-32.
[3]李丹丹,苏小林,阎晓霞,等.储能优化配置关键问题分析[J].电力建设,2016,37(9):70-78.
LI Dandan,SU Xiaolin,YAN Xiaoxia,et al.Principal problems of energy storage optimization allocation[J].Electric Power Construction, 2016,37(9):70-78.
[4]王宁,张建成.基于能量协调控制的混合储能系统容量配置方法[J].电力建设,2016,37(8):72-77.
WANG Ning,ZHANG Jiancheng.Capacity allocation method of hybrid energy storage systembased on energy coordination control[J].Electric Power Construction,2016,37(8):72-77.
[5]向育鹏,卫志农,孙国强,等.基于全寿命周期成本的配电网蓄电池储能系统的优化配置[J].电网技术,2015,39(1):264-270.
XIANG Yupeng,WEI Zhinong,SUN Guoqiang,et al.Life cycle cost based optimal configuration of battery energy storage system in  distribution network[J].Power System Technology,2015,39(1):264-270.
[6]丁明,王波,赵波,等.独立风光柴储微网系统容量优化配置[J].电网技术,2013,37(3):575-581.
DING Ming,WANG Bo,ZHAO Bo,et al.Configuration optimization of capacity of standalone PV-wind-diesel-battery hybrid microgrid[J].Power System Technology,2013,37(3):575-581.
[7]李成,杨秀,张美霞,等.基于成本分析的超级电容器和蓄电池混合储能优化配置方案[J].电力系统自动化,2013,37(18):20-24.
LI Cheng,YANG Xiu,ZHANG Meixia,et al.Optimal configuration scheme for hybrid energy storage system of super-capacitors and batteries based on cost analysis[J].Automation of Electric Power Systems,2013,37(18):20-24.
[8]王成山,于波,肖俊,等,平滑微电网联络线功率波动的储能系统容量优化方法[J].电力系统自动化,2013,37(3):12-17.
WANG Chengshan,YU Bo,XIAO Jun,et al.An energy storage system capacity optimization method for microgrid tie-line power flow stabilization[J].Automation of Electric Power Systems,2013,37(3):12-17.
[9]刘文霞,牛淑娅,石道桂,等.考虑运行策略及投资主体利益的主动配电系统储能优化配置[J].电网技术,2015,39(10):2697-2704.
LIU Wenxia,NIU Shuya,SHI Daogui,et al.Optimal allocation of ADS battery energy storage considering operation strategy and investment subject benefit[J].Power System Technology,2015,39(10):2697-2704.
[10]章美丹,宋晓喆,辛焕海,等.计及网损的配电网电池储能站优化运行策略[J].电网技术,2013,37(8):2123-2128.
ZHANG Meidan,SONG Xiaozhe,XIN Huanhai,et al.Optimal operation strategy of battery energy storage  system in distribution networks with consideration of power losses[J].Power System Technology,2013,37(8):2123-2128.
[11]国宗,韦钢,郭运城,等.面向供电能力提升的配电网储能功率动态优化[J].电力系统保护与控制, 2015,43(19):1-8.
GUO Zong,WEI Gang,GUO Yuncheng,et al.Dynamic optimization of energy storage power in distribution network based on power supply capacity[J].Power System Protection and Control,2015,43(19):1-8.
[12]鲍冠南,陆超,袁志昌,等.基于动态规划的电池储能系统削峰填谷实时优化[J].电力系统自动化,2012,36(12):11-16.
BAO Guannan,LU Chao,YUAN Zhichang,et al.Load shift real-time optimization strategy of battery energy stoyage system based on dynamic programming[J].Automation of Electric Power Systems,2012,36(12):11-16.
[13]杨玉青,牛利勇,田立亭,等.考虑负荷优化控制的区域配电网储能配置[J].电网技术,2015,39(4):1019-1025.
YANG Yuqing,NIU Liyong,TIAN Liting,et al.Configuration of energy storage devices in regional distribution network considering optimal load control[J].Power System Technology,2015,39(4):1019-1025.
[14]阮文骏,王蓓蓓,李扬,等.峰谷分时电价下的用户响应行为研究[J].电网技术,2012,36(7):86-93.
RUAN Wenjun,WANG Beibei,LI Yang,et al.Customer response behavior in time-of-use price[J],Power System Technology,2012,36(7):86-93.
[15]王守相,王成山.现代配电系统分析[M].北京:高等教育出版社,2007:196-202.
WANG Shouxiang,WANG Chengshan.Modern distribution system analysis[M].Beijing:Higher Education Press,2007:196-202.
[16]刘公博,颜文涛,张文斌,等.含分布式电源的配电网动态无功优化调度方法[J].电力系统自动化,2015,39(15):49-54.
LIU Gongbo,YAN Wentao,ZHANG Wenbin,et al.Optimization and dispatching method of dynamic reactive power in distribution network with distributed generators[J].Automation of Electric Power Systems,2015,39(15):49-54.
[17]段开锋.电池储能系统在配电网中的应用研究[D].北京:北京交通大学,2014.
DUAN Kaifeng,The application of battery energy storage system in the distribution network[D].Beijing:Beijing Jiaotong University,2014.
[18]陈沧杨,胡博,谢开贵,等.计入电力系统可靠性与购电风险的峰谷分时电价模型[J].电网技术,2014,38(8):2141-2148.
CHEN Cangyang,HU Bo,XIE Kaigui,et al.A peak-valley TOU price model considering power system reliability andpower purchase risk[J].Power System Technology,2014,38(8):2141-2148.

基金

 

PDF(1432 KB)

Accesses

Citation

Detail

段落导航
相关文章