基于蒙特卡洛模拟的电网建设工程基本预备费测算

侯学良,杨颖蓉,李越   

  1. 华北电力大学工程技术与管理研究所,北京市 102206
  • 出版日期:2014-09-01
  • 作者简介:侯学良 (1966),男,教授,博导,主要从事大型建筑工程实用技术开发、电网建设管理方法、特高压工程施工管理等方面的研究工作; 杨颖蓉 (1989),女,硕士研究生,主要研究方向为电网工程造价管理、特高压工程质量诊断方法,E-mail:yyrfox@hotmail.com; 李越 (1988),女,硕士研究生,主要研究方向为电网工程造价管理、特高压工程风险管理。
  • 基金资助:
    国家自然科学基金(71171081);教育部新世纪优秀人才项目(NCET-11-0633)。

Basic Reserve Fund Calculation of Power Grid Construction Project Based on Monte Carlo Simulation

HOU Xueliang, YANG Yingrong, LI Yue   

  1. Research Institute of Construction Technology and Management, North China Electric Power University, Beijing 102206, China
  • Online:2014-09-01

摘要: 现行的电网建设工程基本预备费的测算主要依据固定费率,而基本预备费是预留来应对不可预见费用的,具有不确定性,仅仅依靠固定费率计取,不能很好地反映实际情况。为此,运用Minitab对影响电网建设工程基本预备费测算的各种因素(变更因素、自然灾害因素、额外建场费因素)的实际分布状况进行拟合分析,根据因素之间的相互关系建立测算模型,并结合实际案例通过Matlab进行蒙特卡洛模拟。模拟结果表明,与现行的测算方法相比,该方法能够很好地反映基本预备费的实际变动情况,可为造价人员合理控制工程造价提供参考。

关键词: 基本预备费测算, 蒙特卡洛模拟, 影响因素, 分布拟合

Abstract: At present, the basic reserve fund calculation method of power grid construction project is mainly based on a fixed rate. However, the basic reserve fund is to deal with the unexpected expenses, it has the characteristic of uncertainty, and cannot reflect the real situation of basic reserve fund though a fixed rate. Therefore, the distribution fitting of influence factors to basic reserve fund calculation were analyzed by Minitab, including change factor, natural disaster factor and extra building cost factor. Then a calculation model was established according to the relationship among the factors. Finally, combined with an actual case, the value of basic reserve fund was calculated by Monte Carlo simulation (MCS) on Matlab. The simulation results show that this calculation method can well reflect the accurate changes of basic reserve fund in actual works, compared with the existing calculation methods, which can provide a reference for related cost personnel to control project cost reasonable

Key words: basic reserve fund calculation, Monte Carlo simulation, influence factors, distribution fitting