特高压交直流混联背景下的江苏电网区外来电消纳能力分析

蔡晖1,孟繁骏2,葛毅1,黄俊辉1, 罗金山2,谢珍建1,祁万春1   

  1. 1. 江苏省电力公司电力经济技术研究院,南京市 210008; 2.国网北京经济技术研究院,北京市  102209
  • 出版日期:2016-02-01
  • 作者简介:蔡晖(1984)男,博士,工程师,主要研究方向为电力系统规划技术; 孟繁骏(1985)男,博士,工程师,主要研究方向为电网规划和智能电网技术; 葛毅(1987)男,博士,工程师,主要研究方向为电力系统规划技术; 黄俊辉(1965) 男,高级工程师,主要研究方向为电网规划研究及管理; 罗金山(1980)男,高级工程师,主要研究方向为电力系统规划技术; 谢珍建(1980)男,高级工程师,主要研究方向为电力系统规划技术; 祁万春(1979) 男,高级工程师,主要研究方向为电力系统规划技术。

Accommodation Capacity of Jiangsu Power Grid External Electricity Based on UHV AC/DC Hybrid

CAI Hui1, MENG Fanjun2, GE Yi1, HUANG Junhui1, LUO Jinshan2, XIE Zhenjian1 , QI Wanchun1   

  1. 1. State Grid Jiangsu Economic Research Institute, Nanjing 210008, China;2. State Power Economic Research Institute, Beijing 102209, China
  • Online:2016-02-01

摘要:

首先介绍了江苏电网及区外来电的概况。针对区外来电的运行现状,从总体受电容量、实际调节特性、电力平衡等角度阐述了区外来电入苏后所带来的问题。在简要分析影响区外来电消纳的主要因素的基础上,对现有区外来电的消纳能力和应对未来区外来电增长的规划方案进行了分析研究。通过分析发现,2020年江苏电网的规划网架可以满足高峰时段受入55 GW区外来电的需要,但需考虑在特高压落点附近配置一定容量的动态无功补偿装置,加强落点附近500   kV网架建设以及优化布局省内事故备用容量。与此同时,规划的江苏2020年主网架能够满足N-2故障或省内一条直流发生双级闭锁故障时安全稳定运行的要求。

关键词: 特高压, 交直流混联, 江苏电网, 区外来电, 消纳能力

Abstract:

This paper firstly introduces the general situation of Jiangsu Power Grid and electric power input from external regions. According to the operation status of electric power input from external regions, we discuss the problems caused by inputting electric power to Jiangsu Power Grid from views of total amount, regulating characteristics, electricity balance, etc. Based on the brief analysis of the main influence factors of electric power accommodation from external regions, we analyze the accommodation capacity of the existing electric power input and the planning schemes for the future input electric power increase. From the analysis it can be found that, the planned grid structure of Jiangsu Power Grid in 2020 can be satisfied to receive 55 GW electricity from outside system; but the dynamic reactive power compensation device with a certain capacity should be configured near the UHV placement, and the 500 kV grid construction should be improvec near the placement and the layout of accident reserve capacity should be optimized in the province. Meanwhile, the planned main grid structure of Jiangsu Power Grid in 2020 can meet the requirements of the safe and stable operation during N-2 fault or double-level locking fault in a DC convertor station.

Key words: UHV, AC/DC hybrid system, Jiangsu Power Grid, input electric power from external regions, accommodation capacity