电力建设 ›› 2011, Vol. 32 ›› Issue (4): 113-116.

• 施工技术 • 上一篇    下一篇

舟山与大陆联网工程大跨越塔安全组立方案

孙伟军,段福平,彭立新,刘金富,宋叶根,杨忠旗,周锡根   

  1. 浙江省送变电工程公司
  • 收稿日期:2011-01-11 修回日期:2011-02-18 出版日期:2011-04-01 发布日期:2011-04-15
  • 通讯作者: 段福平 E-mail:wwwdfp@163.com

The Safety Planning for Erection of the Tower for Zhoushan Island-Mainland Large-crossing Transmission Project

  • Received:2011-01-11 Revised:2011-02-18 Online:2011-04-01 Published:2011-04-15

摘要:

舟山与大陆联网工程大跨越钢管塔高370 m,具有高、重、大的特点,组塔安全风险大。从安全教育培训、安全防护设施系统、安全测控系统、指挥通信系统等四方面进行了安全策划与实施,有效规避了高处坠落、物体打击、机械伤害等危害因素带来的安全风险。

关键词: 高塔, 组立, 安全策划, 大跨越, 钢管塔

Abstract:

The tubular tower for Zhoushan island-mainland large-crossing transmission project, 370 m in height, is characterized by super height, large weight and huge body and has high risks in tower erection. A safety planning is carried out and implemented in terms of safety training, safety protection facilities, safety monitoring system and control and communication system, which effectively avoids the safety risks caused by possible object falling, object impact and mechanical damage.