电厂循环水取排水工程盾构法施工穿越海/江防大堤沉降控制

郑辉

电力建设 ›› 2011, Vol. 32 ›› Issue (5) : 107-110.

PDF(1045 KB)
PDF(1045 KB)
电力建设 ›› 2011, Vol. 32 ›› Issue (5) : 107-110.
施工技术

电厂循环水取排水工程盾构法施工穿越海/江防大堤沉降控制

  • 郑辉
作者信息 +

The Subsidence Control of the Power Plant Circulating Water Draining Engineering Shield Construction Across the Sea/River Defense Dike

  • zheng-hui
Author information +
文章历史 +

摘要

沿海/江发电厂循环水取排水盾构施工工艺的最大难点 是掘进施工需穿越防汛大堤,如控制不好会造成防汛大堤局 部沉降。根据上海某电厂2×1 000 MW机组循环水取排水工 程的特点,制定了盾构法隧道施工穿越海防大堤的沉降控制 措施,有效地控制了大堤沉降。

Abstract

The most difficult point of the power plant across sea/river circulating water & taking catchment engineering shield construction craft is that excavation construction needs to cross the defense dike, which can cause partly dike subsidence without proper control. Based on the characteristics of the circulating water draining engineering from one 2 × 1 000 MW unit in a power plant in Shanghai, the subsidence control measures by the shield construction method was drawn up, which can control the subsidence of dike effectively.

关键词

盾构施工 / 穿越海/江防大堤 / 沉降控制 / 循环水 / 取排水

引用本文

导出引用
郑辉. 电厂循环水取排水工程盾构法施工穿越海/江防大堤沉降控制[J]. 电力建设. 2011, 32(5): 107-110
zheng-hui. The Subsidence Control of the Power Plant Circulating Water Draining Engineering Shield Construction Across the Sea/River Defense Dike[J]. Electric Power Construction. 2011, 32(5): 107-110