采用汽动引风机的1 000 MW级汽轮发电机组RB试验

陈志刚 郝德锋 赵志丹 王家兴 孔德伟 王晓勇

电力建设 ›› 2012, Vol. 33 ›› Issue (8) : 74-77.

PDF(486 KB)
PDF(486 KB)
电力建设 ›› 2012, Vol. 33 ›› Issue (8) : 74-77.
发电技术

采用汽动引风机的1 000 MW级汽轮发电机组RB试验

  • 陈志刚1,郝德锋1,赵志丹1,王家兴2,孔德伟2,王晓勇1
作者信息 +

Runback Test for 1 000 MW Turbine Generator Unit withSteam Turbine-driven IDF

Author information +
文章历史 +

摘要

随着汽动引风机在新建1 000 MW级汽轮发电机组中被逐步应用,相关的辅机故障减负荷(run back,RB)试验受到了越来越多的关注。基于对某台采用汽动引风机的1 000 MW级汽轮发电机组在调试、RB试验中出现问题的分析和总结,提出了送、引风机控制逻辑的优化策略。通过RB试验的严峻考验,证明了该优化策略的可行性,可为其他采用汽动引风机的机组提供相关借鉴。

Abstract

Along with the steam turbine-driven IDF gradually applied in 1 000 MW turbine generator units, the related runback (RB) test has received more and more attention. Based on the analysis and summary of the debugging and RB test problems in a 1 000 MW turbine generator unit using steam turbine-driven IDF, this paper suggested the optimization strategy for the control logic of FDF and IDF. The RB test result proves the feasibility of the optimization strategy, which can provide reference for other units that use the steam turbine-driven IDF.

引用本文

导出引用
陈志刚 郝德锋 赵志丹 王家兴 孔德伟 王晓勇. 采用汽动引风机的1 000 MW级汽轮发电机组RB试验[J]. 电力建设. 2012, 33(8): 74-77
Runback Test for 1 000 MW Turbine Generator Unit withSteam Turbine-driven IDF[J]. Electric Power Construction. 2012, 33(8): 74-77