间接空冷塔桩基方案的选择
Selection of Pile Foundation for Indirect Dry Cooling Tower
针对建设场地的工程地质特点,对2种不同型式的冷却塔地基处理方案进行了比较,确定采用钢筋混凝土灌注桩地基处理方案。采用TSH3SCOQ双曲线自然通风冷却塔结构静力计算程序(有矩理论)对不同桩径(桩径为0.8 m和1.2 m)、不同布桩形式的桩基方案进行了的技术经济比较,最终确定了每对X支柱下布置6根直径1.2 m灌注桩这一合理、经济的桩基设计方案。
According to the geological characteristics of construction site, the treatment schemes for two types of cooling tower foundation are compared, and the reinforced concrete (RC) pile foundation is selected. Then, the technical and economic comparisons are implemented on several pile foundation schemes with different pile diameters (0.8 m and 1.2 m) and pile layout, by using TSH3SCOQ static calculation program (moment theory) for hyperbolic natural draft cooling tower. Finally, a reasonable and economic design scheme of pile foundation is determined, in which six bored piles whose diameters are 12 m are arranged under each pair of X pillar.
indirect dry cooling tower / foundation treatment / optimization design of pile foundation
[1]冯璟. 排烟间接空冷塔的应用条件研究[J]. 电力建设,2009,30(4):64-67.
[2]丛培江,聂冠松,李敬生,等. 间接空冷塔加肋设计[J]. 电力建设,2012,33(4):72-75.
[3]刘楠. CFG桩复合地基在大型间接空冷塔地基处理中的应用[J]. 电力建设,2010,31(6):77-79.
[4]GB 50025—2004 湿陷行黄土地区建筑规范[S]. 北京:中国建筑工业出版社,2004.
[5]刘伟. 强夯法在冷却塔湿陷性地基处理中的应用[J].山东工业大学学报,2001,31(5):497-500.
[6]李毅男.深厚湿陷性黄土地区大型冷却塔地基处理措施[J]. 工业建筑,2008,38(S):721-725.
[7]杜增富. 浅谈桩基工程在火力发电厂中的应用[J]. 电力建设,2000,21(3):40-43.
[8]王玉琴. 孔内深层强夯法在高层建筑地基处理中的应用[J]. 陕西工学院学报,2004,20(2):35-37.
[9]赵会永. 混凝土灌注桩水平承载性能研究[D]. 西安:西安建筑科技大学,2010.
[10]JGJ 94—2008 建筑桩基技术规范[S].北京.中国建筑工业出版社,2008.
AI小编
/
| 〈 |
|
〉 |