基于多层模糊识别的直流联网工程成功度评价体系
Evaluation System of Success Degree Based on Multi-level Fuzzy Recognition for DC Interconnection Project
针对目前直流联网工程没有统一、规范的工程评价标准的现状,结合此类工程投资、建设及运维特点,从项目过程评价、项目经济评价、项目影响评价、项目技术评价、项目管理评价和项目目标评价6个方面构建了直流联网工程成功度评价指标体系。鉴于指标体系的多层次性,采用模糊识别方法,对指标逐级进行成功度的模糊识别。最后通过算例,分析并验证了多层模糊识别模型的可行性。该指标体系和成功度评价模型对于客观、准确地评价直流联网工程的成功度具有一定的参考价值。
Because there is no uniform evaluation standard for DC interconnection project, combined with the characteristics of the project’s investment, construction and operation, the evaluation index system of success degree for DC interconnection project is built in this paper from six aspects: the process evaluation, the economic evaluation, the impact evaluation, the management evaluation, the technology evaluation and the target evaluation. In view of the multiple levels of the index system, the success degree at each level is recognized by fuzzy recognition method. Finally, the feasibility of multi-level fuzzy recognition model is analyzed and verified by examples. The index system and the evaluation model have the certain reference value for the objective and accurate evaluation of success degree of DC interconnection project.
DC interconnection project / evaluation system of success degree / fuzzy recognition
[1]苏永波.基于模糊层次分析法的工程项目合作伙伴的选择[J].价值工程,2012(8):31-33.
[2]卢福强,薛岩松. 基于随机层次分析法的虚拟企业风险评价[J]. 信息与控制,2012, 41(1):110-116.
[3]王敬敏,朱益平.基于模糊层次分析法的变电站建设项目节能综合评价研究[J].华东电力, 2012, 40(4) : 553-555.
[4]卢艳超, 张彩庆. 用非线性化的方法对主成分分析法的改进[J].统计与决策,2005(9):127-128.
[5]丁乐群, 李光辉, 董术涛. 基于DEA的发电建设项目进度、成本、质量联合控制[J].电力建设,2010,31(8):100-103.
[6]黄静, 马宏忠, 纪卉, 等.密切值法在电能质量综合评价中的应用[J].继电器,2008,36(3):60-63.
[7]周林,栗秋华,张凤.遗传投影寻踪插值模型在电能质量综合评估中的应用[J].电网技术,2007,31(7):32-35.
[8]续艳艳,姚俭. 因子分析和BP神经网络在区域人才创新能力评价中的应用[J]. 技术与创新管理,2012,33(2):130-133.
[9]陈连栋,吕春梅. 基于模糊综合评判的电力风险评估方法的研究[J]. 电力科学与工程, 2010(11) : 50-54.
[10]戴喆,刘川. 模糊层次分析法在电力通信中的应用[J].价值工程,2011(21) : 26-27.
国家电网公司发展咨询项目(B3441012G001)。