[1]国家电网公司. 国家电网公司促进风电发展白皮书[R]. 北京:国家电网公司,2011.[2]Ni M,Yang Z X. By leaps and bounds:Lessons learned from renewable energy growth in China[J]. IEEE Power & Energy Magazine,2012,10(2):37-43.[3]Holttinen H,Orths A G,Eriksen P B,et al. Currents of change-European experience and perspectives with high wind penetration levels[J]. IEEE Power & Energy Magazine,2011,9(6):47-59.[4]Piwko R,Meibom P,Holttinen H,et al. Penetrating insights-lessons learned from large-scale wind power integration[J] . IEEE Power & Energy Magazine,2012,10(2):44-52.[5]罗旭,马珂.美国德克萨斯州电力可靠性委员会在风电调度运行管理方面的经验和启示[J].电网技术,2011,35(10):140-146.[6]鲁宗相,闵勇. 基于功率预测的波动性能源发电的多时空尺度调度技术[J].电力科学与技术学报,2012,27(3):28-33.[7]薛峰,常康,汪宁渤.大规模间歇式能源发电并网集群协调控制框架[J].电力系统自动化,2011,35(22):45-53.[8]刘德伟,黄越辉,王伟胜,等.考虑调峰和电网输送约束的省级系统风电消纳能力分析[J].电力系统自动化,2011,35(22):77-81.[9]The European Wind Energy Association(EWEA). Large scale integration of wind energy in the European power supply: Analysis,issues and recommendation[EB/OL]. 2005.[2013-01-22] http://www.ewea.org/fileadmin/ewea_documents/documents/publications/grid/051215_Grid_report.pdf.[10]肖创英,汪宁渤,陟晶,等.甘肃酒泉风电出力特性分析[J].电力系统自动化,2010,34(17):64-67.[11]Hetzer J,Yu D C,Bhattarai K. An economic dispatch model incorporating wind power[J]. IEEE Trans on Energy Conversion,2008,23(2):603-611.[12]Liu X,Xu W. Minimum emission dispatch constrained by stochastic wind power availability and cost[J]. IEEE Trans on Power System,2010,25(3):1705-1713.[13]林卫星,文劲宇,艾小猛,等.风电功率波动特性的概率分布研究[J].中国电机工程学报,2012,32(1):38-46.[14]李剑楠,乔颖,鲁宗相,等.大规模风电多尺度出力波动性的统计建模研究[J].电力系统保护与控制,2012,40(19):7-13.[15]Zhang N,Kang C Q,Duan C G,et al. Simulation methodology of multiple wind farms operation considering wind speed correlation[J]. International Journal of Power and Energy Systems,2010,30(4):264-173.[16]Villanueva D,Feijóo A,Pazos J L. Simulation of correlated wind speed data for economic dispatch evaluation[J]. IEEE Trans on Sustainable Energy,2012,3(1):142-149.[17]Srensen P,Mann J,Paulsen U S,et al. Wind farm power fluctuations,Chapter 25 of wind energy proceeding of the euromech colloquium[M]. Springer Berlin Heidelberg,2007:139-145.[18]Srensen P,Cutululis N A,Vigueras-Rodríguez A,et al. Power fluctuations from large wind farms[J]. IEEE Trans on Power System,2007,22(3):958-965.[19]Giebel G,Srensen P,Holttinen H. Forecast error of aggregated wind power[EB/OL].[2013-01-22]. http://www.trade- wind.eu/fileadmin/documents/publications/D2.2_Estimates_of_forecast_error_for_aggregated_wind_power_Final.pdf.[20]袁铁江,晁勤,吐尔逊·伊不拉音,等. 大规模风电并网电力系统动态清洁经济优化调度的建模[J]. 中国电机工程学报,2010,30( 31):7-13.[21]王洪涛,何成明,房光华,等. 计及风电预测误差带的调度计划渐进优化模型[J]. 电力系统自动化,2011,35(22):131-135.[22]张昭遂,孙元章,李国杰,等. 计及风电功率不确定性的经济调度问题求解方法[J].电力系统自动化,2011,35(22):125-130.[23]Bludszuweit H,Domínguez-Navarro J A,Llombart A. Statistical analysis of wind power forecast error[J]. IEEE Trans on Power System,2008,23(3):983-991.[24]Fabbri A,GomezSanRoman T,RivierAbbad J,et al. Assessment of the cost associated with wind generation prediction errors in a liberalized electricity market[J]. IEEE Trans on Power Systems,2005,20(3):1440-1446.[25]Tewari S,Geyer C J,Mohan N. A statistical model for wind power forecast error and its application to the estimation of penalties in liberalized markets[J]. IEEE Trans on Power System,2011,26(4):2031-2039.[26]Tuohy A,Meibom P,Denny E,et al. Unit commitment for systems with significant wind penetration[J]. IEEE Trans on Power System,2009,24(2):592-601.[27]王小海,齐军,侯佑华,等.内蒙古电网大规模风电并网运行分析和发展思路[J].电力系统自动化,2011,35(22):90-96.[28]张伯明,吴文传,郑太一,等.消纳大规模风电的多时间尺度协调的有功调度系统设计[J].电力系统自动化,2011,35(1):1-6.[29]Wang J H,Shahidehpour M,Li Z Y. Security-constrained unit commitment with volatile wind power generation[J]. IEEE Trans on Power System,2008,23(3):1319-1327.[30]Ruiz P A,Philbrick C R,Zak E. Uncertainty management in the unit commitment problem[J]. IEEE Trans on Power System , 2009,24(2):642-651.[31]Pappala V S,Erlich I,Rohrig K,et al. A stochastic model for the optimal operation of a wind-thermal power system[J ]. IEEE Trans on Power System,2009,24(2):940-950.[32]Bouffard F,Galiana F D. Stochastic security for operations planning with significant wind power generation[J]. IEEE Trans on Power System,2008,23(2):306-316.[33]Wang Q F,Guan Y P,Wang J H. A chance-constrained two-stage stochastic program for unit commitment with uncertain wind power output[J]. IEEE Trans on Power System,2012,27(1):206-215.[34]Constantinescu E M,Zavala V M,Rocklin M,et al. A computational framework for uncertainty quantification and stochastic optimization in unit commitment with wind power generation[J]. IEEE Trans on Power System,2011,26(1):431- 441.[35]Li X H,Jiang C W. Short-term operation model and risk management for wind power penetrated system in electricity market[J]. IEEE Trans on Power System,2011,26(2):932-939.[36]周任军,姚龙华,童小娇,等.采用条件风险方法的含风电系统安全经济调度[J]. 中国电机工程学报,2012,32(1):56-63.[37]周玮,孙辉,顾宏,等. 计及风险备用约束的含风电场电力系统动态经济调度[J]. 中国电机工程学报,2012,32(1):47-55.[38]张国强,吴文传,张伯明.考虑风电接入的有功运行备用协调优化[J].电力系统自动化,2011,35(12):15-19,46.[39]Matos M A,Bessa R J. Setting the operating reserve using probabilistic wind power forecasts[J]. IEEE Trans on Power System,2011,26(2):594-603.[40]王彩霞,乔颖,鲁宗相. 考虑风电效益的风火互济系统旋转备用确定方式[J]. 电力系统自动化,2012,36(4):16-21.[41]Gautam D,Goel L,Ayyanar R,et al. Control strategy to mitigate the impact of reduced inertia due to doubly fed induction generators on large power systems[J]. IEEE Trans on Power System,2011,26(1):214-224.[42]Mullane A,O'Malley M. The inertial response of induction-machine-based wind turbines[J]. IEEE Trans on Power System ,2005,20(3):1496-1503.[43]Banakar H,Luo C L,Ooi B T. Impacts of wind power minute-to-minute variations on power system operation[J]. The inertial Response of Induction-Machine-Based Wind Turbines,2008,23(1):150-160. |