苏州1 000 kV特高压变电站500 kV电气主接线方案技术经济分析

王昊,王展,陈斌

电力建设 ›› 2013, Vol. 34 ›› Issue (4) : 43-46.

PDF(542 KB)
PDF(542 KB)
电力建设 ›› 2013, Vol. 34 ›› Issue (4) : 43-46.
输配电技术

苏州1 000 kV特高压变电站500 kV电气主接线方案技术经济分析

  • 王昊,王展,陈斌
作者信息 +

Technical and Economic Analysis of 500 kV Main Electrical Connection Scheme in Suzhou 1 000 kV UHV Substation

  • WANG Hao, WANG Zhan1, CHEN Bin 2
Author information +
文章历史 +

摘要

随着特高压电网的快速发展,特高压变电站的电气主接线对电网的安全可靠运行起着越来越重要的作用,因此选择合适的电气主接线是特高压变电站建设中的一个重要课题。结合苏州1 000 kV特高压变电站的特性分析了500 kV电气主接线方案,对双母线接线和3/2接线进行了详细的技术经济比较,推荐苏州特高压变电站500 kV主接线采用双母线接线。该接线不仅能够满足电网可靠性的要求,而且调度灵活、扩建方便、占地小、投资省。

Abstract

With the rapid development of UHV power grid, the main electrical connection of UHV substation becomes more and more important to the safe and reliable operation of power grid. Therefore, the selection of suitable main electrical connection is a key work in the construction of UHV substations. According to the characteristics of Suzhou 1 000 kV UHV substation, he 500 kV main electrical connection scheme is analyzed in this paper. The techno-economic comparison between double-bus connection and two-thirds connection is carried out and the 500 kV main electrical connection of Suzhou UHV substation is suggested to adopt the double-bus connection, which not only could meet the requirements of the reliability of power grid, but also have some advantages of flexible scheduling, convenient expansion, small occupation of land and low investment.

关键词

特高压变电站 / 电气主接线 / 可靠性 / 双母线接线 / 3/2接线

Key words

UHV substation / main electrical connection / reliability / double-bus connection / two-thirds connection

引用本文

导出引用
王昊,王展,陈斌. 苏州1 000 kV特高压变电站500 kV电气主接线方案技术经济分析[J]. 电力建设. 2013, 34(4): 43-46
WANG Hao, WANG Zhan, CHEN Bin. Technical and Economic Analysis of 500 kV Main Electrical Connection Scheme in Suzhou 1 000 kV UHV Substation[J]. Electric Power Construction. 2013, 34(4): 43-46

参考文献

[1]GB 50697—2011 1 000  kV变电站设计规范[S]. 北京:中国计划出版社,2011.



[2]李勇,黄宝莹,鲁宗相,等. 基于电网协调发展的特高压变电站电气主接线设计原则[J]. 电力建设,2011,32(1): 27-33.



[3]国家电网公司. 国家电网总体规划设计[R].北京:国家电网公司, 2009.



[4]中国电力工程顾问集团、国网北京经济技术研究院.淮南—南京—上海1 000  kV交流输变电工程可行性研究[R].北京:中国电力工程顾

 


问集团、国网北京经济技术研究院, 2010.



[5]Billinton R,  Chen H, Zhou J Q, Individual Generating Station Reliability Assessment[J], IEEE Transaction on Power

 


System, 1999,14(12):4



[6]Billinton R, Ronald N. Allan, Reliability Evaluation of Power System (second edition)[M], Plenum Press, 1994.



[7]Billinton R, Ronald N. Allan, Reliability Evaluation of Engineering System: Concepts and Techniques[M]. Pitman Press,

 


1983.



[8]郭永基.苏联若干电工产品可靠性指标统计[J]. 电工技术,1989(3):8-13.



[9]CIGRE WG13.06. Studies on the Reliability of Single Pressure SF6-Gas High-voltage Circuit Breakers[S]. 1996.



[10]CAE. Forced Outage Performance of Transmission Equipment[S]. 1996.



[11]鲁宗相,郭永基.水电站电气主接线可靠性评估[J].电力系统自动化,2001,25(18):16-19.



[12]中国电工技术学会特高压输变电技术考察团. 俄罗斯、乌克兰超、特高压输变电技术发展近况[J]. 电力设备,2003,4(2):49-56.

PDF(542 KB)

Accesses

Citation

Detail

段落导航
相关文章
AI小编
你好!我是《电力建设》AI小编,有什么可以帮您的吗?

/