宝鸡—德阳±500 kV直流输电工程极1运行极2调试的安全技术措施

王茂忠 李林 种芝艺 黄杰

电力建设 ›› 2011, Vol. 32 ›› Issue (10) : 78-81.

PDF(1460 KB)
PDF(1460 KB)
电力建设 ›› 2011, Vol. 32 ›› Issue (10) : 78-81.
运行与管理

宝鸡—德阳±500 kV直流输电工程极1运行极2调试的安全技术措施

  • 王茂忠1,李林2,种芝艺1,黄杰1
作者信息 +

Discussion on the Safety Technical Measures for the ±500 kV Baoji-Deyang HVDC Project in the Case of Pole II under

Author information +
文章历史 +

摘要

宝鸡—德阳±500 kV直流输电工程极1、极2系统分阶段投运,为保证在极2及双极系统调试期间极1系统能够安全稳定运行,必须对1极进行安全隔离。针对极1、极2系统之间的相互影响因素进行了详细分析,并归纳总结,提出了相应的软件、硬件安全技术隔离措施,可供后续有关直流工程建设和运行参考。

Abstract

In the ±500 kV Baoji-Deyang HVDC project, Pole I and Pole II will put into operation in different stages. During the commissioning test of Pole II, the safe and stabe operation of Pole I is guaranteed by the isolation between two pole. In this paper, the interaction between two pole is analyzed in detail, factors are given and summarized. The isolation measures on both software and hardware are proposed, which can be further referenced by similar subsequent projects.

关键词

直流输电 / 调试 / 安全 / 软件隔离 / 硬件隔离

Key words

HVDC / commissioning test / safety / software isolation / hardware isolation

引用本文

导出引用
王茂忠 李林 种芝艺 黄杰. 宝鸡—德阳±500 kV直流输电工程极1运行极2调试的安全技术措施[J]. 电力建设. 2011, 32(10): 78-81
Discussion on the Safety Technical Measures for the ±500 kV Baoji-Deyang HVDC Project in the Case of Pole II under[J]. Electric Power Construction. 2011, 32(10): 78-81

PDF(1460 KB)

Accesses

Citation

Detail

段落导航
相关文章
AI小编
你好!我是《电力建设》AI小编,有什么可以帮您的吗?

/