500 kV同塔四回路西江大跨越基础大体积混凝土施工技术

陈志辉

电力建设 ›› 2011, Vol. 32 ›› Issue (12) : 105-109.

PDF(1263 KB)
PDF(1263 KB)
电力建设 ›› 2011, Vol. 32 ›› Issue (12) : 105-109.
施工技术

500 kV同塔四回路西江大跨越基础大体积混凝土施工技术

  • 陈志辉
作者信息 +

Construction Technology of Mass Concrete for 500 kV Quadri-circuit Xijiang Large Crossing Tower Foundation

Author information +
文章历史 +

摘要

以500 kV同塔四回路西江大跨越工程跨越塔基础承台大体积混凝土施工为例,通过对施工阶段大体积混凝土浇筑体裂缝控制的热工计算,制定了混凝土配合比优化、入模温度控制、整体分层浇筑、“内散外蓄”综合养护等技术措施,有效地指导了施工,成功避免了大体积混凝土有害裂缝的产生,收到了较好的效果。

Abstract

The construction of mass concrete for crossing tower pile foundation in 500 kV quadricircuit Xijiang large crossing transmission line project is considered. Based on the thermal calculation of mass concrete crack control during the construction stage, some technical measures are formulated including the optimization of concrete mixture, concrete temperature control, concrete layered pouring, and integrated conservation of internal distribution and external store etc, so that the construction is effectively guided, the harmful mass concrete cracks successfully avoided, and good effects received.

关键词

同塔四回路 / 大跨越基础 / 大体积混凝土 / 施工技术 / 混凝土裂缝

引用本文

导出引用
陈志辉. 500 kV同塔四回路西江大跨越基础大体积混凝土施工技术[J]. 电力建设. 2011, 32(12): 105-109
Construction Technology of Mass Concrete for 500 kV Quadri-circuit Xijiang Large Crossing Tower Foundation[J]. Electric Power Construction. 2011, 32(12): 105-109

PDF(1263 KB)

Accesses

Citation

Detail

段落导航
相关文章
AI小编
你好!我是《电力建设》AI小编,有什么可以帮您的吗?

/