1 000 MW压水堆核电站辅助设施管道施工

廖建华

电力建设 ›› 2011, Vol. 32 ›› Issue (7) : 120-123.

PDF(380 KB)
PDF(380 KB)
电力建设 ›› 2011, Vol. 32 ›› Issue (7) : 120-123.
施工技术

1 000 MW压水堆核电站辅助设施管道施工

  • 廖建华
作者信息 +

Pipe Construction of Balance of 1 000 MW Pressurized Water Reactor Nuclear Power Plant

Author information +
文章历史 +

摘要

主要探讨了核电站辅助设施(balance of the plant,BOP)管道施工中出现的一些技术问题,如施工质量的可追溯性、共用支架防变形、电抛光管内部的洁净控制、沟槽式管件的应用等,并结合实际制订了相应的技术措施。这些措施通过现场的实际操作检验,证实了简单、有效,为后续核电BOP管道施工提供了借鉴。

Abstract

The technical problems, such as the traceability of the construction quality, anti-deformation of shared support, clean control inside the electro-polished tube, and applications of groove pipes, are discussed in this paper, which occur in the pipe construction of balance of nuclear power plant. Furthermore, the corresponding technical measures are established combining with the practical condition, which are proved to be simple and effective by the on-site inspection, providing references for the pipeline construction of balance of nuclear power plant in the future.

关键词

压水堆核电站 / 辅助设施 / 管道施工 / 电抛光管 / 沟槽式管件 / 紧固力矩

Key words

pressurized water reactor nuclear power plant / supporting facilities / pipeline construction / electro-polished tube / groove pipe / tightening torque

引用本文

导出引用
廖建华. 1 000 MW压水堆核电站辅助设施管道施工[J]. 电力建设. 2011, 32(7): 120-123
Pipe Construction of Balance of 1 000 MW Pressurized Water Reactor Nuclear Power Plant[J]. Electric Power Construction. 2011, 32(7): 120-123

PDF(380 KB)

Accesses

Citation

Detail