摘要

结合目前国内外先进的烟气脱硫技术特点,对热电厂(2×350 MW+2×50 MW)机组的海水脱硫方案,从保障电厂安全可靠运行、优化电厂脱硫及全厂总体布置、节省项目投资及降低运行费用等方面进行了技术经济比较和优化建议,推荐了适合本类工程的海水脱硫系统最佳方案。

Abstract

Combined with the advanced flue gas desulfurization(FGD) technology at home and abroad at present, the technical and economic comparisons and optimization proposals are implemented of seawater desulfurization plan for two 350 MW and two 50 MW units in the thermal power plant, including ensuring the safe and reliable operation of the plants, optimizing SWFGD(seawater FGD) system and general layout, saving the project investments and lowering operating costs, The preferred plan of SWFGD system for this kind of project is recommended.

关键词

海水脱硫 / 热电厂 / 比选 / 技术经济分析 / 烟气脱硫 / 总体布置

引用本文

导出引用
崔箫. 热电厂不同容量机组海水脱硫方案比选[J]. 电力建设. 2011, 32(8): 91-94
Comparison of Seawater Desulfurization for Different Capacity Units in Thermal Power Plant[J]. Electric Power Construction. 2011, 32(8): 91-94

PDF(351 KB)

Accesses

Citation

Detail

段落导航
相关文章
AI小编
你好!我是《电力建设》AI小编,有什么可以帮您的吗?

/