高原冻土区输电铁塔基础施工关键技术

靳义奎 梁来先 刘军 高鹏飞

电力建设 ›› 2012, Vol. 33 ›› Issue (10) : 94-97.

PDF(2465 KB)
PDF(2465 KB)
电力建设 ›› 2012, Vol. 33 ›› Issue (10) : 94-97.
施工技术

高原冻土区输电铁塔基础施工关键技术

  • 靳义奎1,梁来先1,刘军1,高鹏飞2
作者信息 +

Key Technology of Foundation Construction for Transmission Tower in Plateau Frozen Soil District

Author information +
文章历史 +

摘要

格尔木—拉萨±400 kV直流输电线路工程沿线平均海拔为4 650 m。基于该工程,针对青藏高原冻土地区输电线路基础施工的特点和难点,研究杆塔基础施工关键技术,并提出了相应的基础施工方案,可为我国高海拔冻土地区输电线路施工提供参考。

Abstract

The average elevation of ±400 kV DC Golmud-Lhasa transmission line project is 4 650 m. Based on this project, according to the characteristics and difficulties of foundation construction in plateau frozen soil district in Tibetan, this paper studied the key technologies of tower foundation construction, and suggested some foundation construction schemes, which could provide references for other transmission line constructions in plateau frozen soil district in China.

引用本文

导出引用
靳义奎 梁来先 刘军 高鹏飞. 高原冻土区输电铁塔基础施工关键技术[J]. 电力建设. 2012, 33(10): 94-97
Key Technology of Foundation Construction for Transmission Tower in Plateau Frozen Soil District[J]. Electric Power Construction. 2012, 33(10): 94-97
中图分类号: TU752   

基金

国家重大工程