第三代核电站大型结构模块吊装分析

叶志燕 刘建卫 储艳春

电力建设 ›› 2012, Vol. 33 ›› Issue (2) : 100-103.

PDF(2396 KB)
PDF(2396 KB)
电力建设 ›› 2012, Vol. 33 ›› Issue (2) : 100-103.
施工技术

第三代核电站大型结构模块吊装分析

  • 叶志燕,刘建卫,储艳春
作者信息 +

Lifting Analysis of Large-sized Structural Module in Third Generation Nuclear Power Plant

Author information +
文章历史 +

摘要

第三代核电站大规模采用模块化建造技术,缩短建设工期的同时增加了施工难度。为将大型结构模块安全准确地吊装就位,对结构模块吊装进行有限元分析,确定模块吊装时的最大变形和应力,并对构件进行规范验算,结果表明模块能满足吊装要求。有限元分析结果为结构模块的安全就位提供强有力的理论支撑。

Abstract

Modular construction is widely used in third generation nuclear power plants, which shortens the construction period but increases difficulty of construction. In order to make structural module lift safely and accurately, the maximum deformation and stress for lifting modules are determined by finite element analysis. In addition, the components are evaluated standardly, showing that the modules could satisfy the lifting requirement. Results of finite element analysis provide a strong theoretical support for structural module lifting.

引用本文

导出引用
叶志燕 刘建卫 储艳春. 第三代核电站大型结构模块吊装分析[J]. 电力建设. 2012, 33(2): 100-103
Lifting Analysis of Large-sized Structural Module in Third Generation Nuclear Power Plant[J]. Electric Power Construction. 2012, 33(2): 100-103

PDF(2396 KB)

Accesses

Citation

Detail

段落导航
相关文章
AI小编
你好!我是《电力建设》AI小编,有什么可以帮您的吗?

/