DG3110/26.15型超超临界直流锅炉吊装方法探讨
Discussion of Hoisting Method for DG3110/26.15 Ultra-Supercritical Once-through Boiler
论述了沁北电厂三期扩建工程2×1 000 MW机组DG3110/26.15-Ⅱ1型直流锅炉吊装的关键技术。根据锅炉设备参数、布置方式及自有吊装机械资源, 综合施工工序和安全、质量、成本等因素,给出了合理的吊装方案(包括钢架和受热面组件吊装方案),实施此方案后取得了良好的效果。该工程锅炉的吊装经验对于同类工程具有借鉴意义。
The key hoisting technology for DG3110/26.15-Ⅱ1 once-through boiler of 2×1 000 MW units in the third stage extension project of Qinbei Power Plant is introduced in this paper. According to the boiler parameters, arrangement mode, and considering own mechanical resource of hoisting and process, safety, quality and cost in construction, a reasonable hoisting scheme is suggested, including the steel frame and heating surface components, which has been proved with beneficial effect. The experience also has referencial significance to the same type boiler hoisting.
ultra-supercritical units / boiler / steel frame / water wall / hoisting
[1]东方锅炉(集团)股份有限公司.锅炉安装说明书14S-M[G].德阳:东方锅炉(集团)股份有限公司,2009.
[2]郑州科润电机工程有限公司.FZQ-2400附壁吊车说明书及负荷表[G].郑州:国电郑州机械设计研究所,2007.
[3]利勃海尔公司.LR-1750履带吊说明书及负荷表[G].德国:利勃海尔公司,2008.
[4]河南第二火电建设公司.华能沁北电厂三期2×1 000 MW机组锅炉施工组织设计[G].郑州:河南第二火电建设公司,2009.
[5]冯志毅.锅炉安装常见要点及其质量控制要点[J].应用能源技术,2009(2):27-29.
[6]王运法.锅炉主力吊装机械的选择[J].水利电力机械,2007(1):46-49.
[7]河南第二火电建设公司.华能沁北电厂三期2×1 000 MW机组锅炉顶板梁吊装方案[R].郑州:河南第二火电建设公司,2010.
[8]锦峰,芮晓明,马晓勇.电站锅炉吊装干涉分析模型及其数据结构[J].现代电力,2002(3):33-36.
[9]河南第二火电建设公司.华能沁北电厂三期2×1 000 MW机组锅炉受热面吊装方案[R].郑州:河南第二火电建设公司,2010.
[10]中国电力建设企业协会.电力建设施工质量验收及评价规程:锅炉机组[S].北京:中国电力建设企业协会,2009.
AI小编
/
| 〈 |
|
〉 |