Accurate Calculation Method for Neutral Reactor of EHV Double-Circuit Line

ZHANG Jiankang1, LIN Jingyun2, LIN Jun3   

  1. 1. Northwest China Grid Company Limited, Xi'an 710048, China;2. Huaneng Fuzhou Power Plant, Fuzhou 350200, China;3.Fujian University of Technology, Fuzhou 350108, China
  • Online:2014-08-01

Abstract: To solve the accurate calculation problem of secondary arc current and recovery voltage in non-complete-phase operation after single-phase grounding fault of double-circuit line with shunt reactor and neutral reactor, this paper used eigen-model decomposition method to decouple zero sequence parameter in double-circuit line, and proposed the formula for non-complete-phase operation of double-circuit line based on its measured parameters: positive/negative sequence impedance, electrical susceptance, zero sequence self-impedance and mutual impedance, zero sequence self-susceptance and mutual susceptance. The results show that the calculation result of secondary arc current and recovery voltage at fault point can provide a reliable basis for the parameter determination of neutral reactor in double-circuit line, which is valuable to engineering application.

Key words: double circuit, fault calculation, neutral reactor, eigen-model, distribute parameter