ELECTRIC POWER CONSTRUCTION ›› 2014, Vol. 35 ›› Issue (3): 107-112.doi: 10.3969/j.issn.1000-7229.2014.03.021

Previous Articles    

Link Transitive Relation and Evaluation Model of Comprehensive Schedule Risk Indicators Group in Grid Project

LI Jiayu, RAO Rao, YAN Yan, GAN Jingshuang, TAN Zhongfu   

  1. Economics and Management Department of North China Electric Power University, Beijing 102206, China
  • Online:2014-03-01

Abstract:

 In order to achieve the comprehensive schedule risk management of grid project, based on enterprise risk management (ERM) framework, a comprehensive schedule risk management system was formed, which concluded five subsystems: target system, environment system, organization system, process system and method system. Meanwhile, it presented the risk research method with circular transmission. Further, based on the research framework, it explored the risk link relations on the base of a new concept of “risk map” and built a risk evaluation model, then quantified the impact of each risk value via fuzzy evaluation. Finally, key risk with higher degree of influence was obtained, which could provide a reference for risk prevention and control. 

Key words: enterprise risk management (ERM), schedule management, comprehensive schedule risk management system, risk map, risk evaluation