Discussion on the Safety Technical Measures for the ±500 kV Baoji-Deyang HVDC Project in the Case of Pole II under

Electric Power Construction ›› 2011, Vol. 32 ›› Issue (10) : 78-81.

PDF(1460 KB)
PDF(1460 KB)
Electric Power Construction ›› 2011, Vol. 32 ›› Issue (10) : 78-81.

Discussion on the Safety Technical Measures for the ±500 kV Baoji-Deyang HVDC Project in the Case of Pole II under

Author information +
History +

Abstract

In the ±500 kV Baoji-Deyang HVDC project, Pole I and Pole II will put into operation in different stages. During the commissioning test of Pole II, the safe and stabe operation of Pole I is guaranteed by the isolation between two pole. In this paper, the interaction between two pole is analyzed in detail, factors are given and summarized. The isolation measures on both software and hardware are proposed, which can be further referenced by similar subsequent projects.

Key words

HVDC / commissioning test / safety / software isolation / hardware isolation

Cite this article

Download Citations
Discussion on the Safety Technical Measures for the ±500 kV Baoji-Deyang HVDC Project in the Case of Pole II under[J]. Electric Power Construction. 2011, 32(10): 78-81
PDF(1460 KB)

Accesses

Citation

Detail

Sections
Recommended

/