Impact of Heating Surface Pre-purge on Boiler Steam Pipe-blowing inSupercritical Unit
Electric Power Construction ›› 2012, Vol. 33 ›› Issue (7) : 66-68.
PDF(565 KB)
PDF(565 KB)
Impact of Heating Surface Pre-purge on Boiler Steam Pipe-blowing inSupercritical Unit
This paper introduced the heating surface purging process during the installation of the supercritical once-through boiler in Huaneng Dongfang Power Plant. The comparison of pipe-blowing date and effect between same type units was investigated. The result shows that the heating surface pre-purge during the installation process is worth popularizing, because it can significantly reduce the boiler’s ignition time and pipe-blowing time, as well as save fuel, desalting water, electricity, the way is worth promotion.
/
| 〈 |
|
〉 |