Analysis on Partial Frequency Accident of Turbine

DANG Xiaojian, LI Zhihua, LIAO Junlin,WANG Zheng

Electric Power Construction ›› 2013, Vol. 34 ›› Issue (4) : 95-98.

PDF(522 KB)
PDF(522 KB)
Electric Power Construction ›› 2013, Vol. 34 ›› Issue (4) : 95-98.

Analysis on Partial Frequency Accident of Turbine

  • DANG Xiaojian1, LI Zhihua1,2, LIAO Junlin1,WANG Zheng1
Author information +
History +

Abstract

A shut-down accident occurred in a power plant because of turbine’s partial frequency operation. The main reasons of frequent fluctuations of steam temperature behind high and low pressure bypass in HP casing exhaust lie in high metal temperature, which is caused by the closed non-return valve and the heavy turbine load. Meanwhile, the harm to turbines caused by the removal of high pressure cylinder under large load is analyzed. Finally, some suggestions on logical configuration of partial frequency protection, desuperheating water of low pressure bypass and non-return valve are proposed in HP casing exhaust. The operation practice show that the logical configuration scheme could avoid accidents and be safe and reliable.

Key words

turbine / partial frequency / rotor life / HP casing exhaust non-return valve

Cite this article

Download Citations
DANG Xiaojian, LI Zhihua, LIAO Junlin,WANG Zheng. Analysis on Partial Frequency Accident of Turbine[J]. Electric Power Construction. 2013, 34(4): 95-98

References

[1]黄旭鹏,冯庭有. 1 036   MW超超临界汽轮机停机快冷方法应用研究[J]. 电力建设,2011,32(5):72-75.



[2]周箐,殷学友.汽轮机组启动方式特点研究与探讨[J].电站系统工程,2009,25(6):34-36.



[3]周兰欣,李卫华,王勇. 直接空冷机组运行特点分析及对策[J]. 电力建设,2009,30(4):56-60.



[4]许德刚.汽轮机最佳启动方式研究[J]. 河南科技,1996,14(4):409-413.



[5]旷仲和.带高压一级旁路的1 000   MW汽轮机不设高排逆止门的布置改进[J].热力透平,2007,36(4):212-260.



[6]马呈霞,秦睿,钱康,等. 直接空冷机组背压模糊控制方法[J]. 电力建设,2012,33(1):6-11.



[7]谢尉扬. 西门子超超临界汽轮机跳闸条件分析[J]. 电力建设,2012,33(6):75-77.



[8]冯利法,闫志鹏,徐治皋. 大型汽轮机运行状态的可拓评价理论与系统开发[J]. 汽轮机技术,2009,51(2):125-128.



[9]钱立军,蒋东翔,战祥森. 汽轮机运行参数偏差对经济性能影响的分析方法[J]. 汽轮机技术,2001,43(3):147-149,136.



[10]冯利法,徐治皋. 大型汽轮机运行状态物元模型及可拓评价方法[J]. 华东电力,2008(7):85-87.

PDF(522 KB)

Accesses

Citation

Detail

Sections
Recommended

/