ELECTRIC POWER CONSTRUCTION ›› 2013, Vol. 34 ›› Issue (7): 95-99.

Previous Articles     Next Articles

Analysis and Treatment on Circuit Breaker Fault at Generator Outlet

 

LI Zhanbao1,ZHOU Changhua1,WANG Feng1,QU Shaobo1,  WANG Zhe1, WANG Xin2,LIU Longkuo2,YAN Zhong2
  

  1. 1.Shandong Electric Power Construction No.2 Company, Jinan 250100, China; 2.Shandong Topower Engineering Consulting Co., Ltd., Jinan 250100, China
  • Online:2013-07-01

Abstract:

During the start-up commissioning of No.1 unit (350 MW) in India Kamalanga Power Plant, two-phase short-circuit fault occurred at generator outlet during the process of synchronization. The fault causes were analyzed based on fault records, computer messages and other fault information. After the replacement of circuit breaker, the detection test for main transformer, the circuit breaker performance test, short circuit and open circuit performance test for generator, as well as the load test for units were carried out, and the results were compared with the detection test results before fault, in order to confirm that the main transformer and generator could be able to put into operation with the safety and reliability not being changed. Finally, countermeasures were proposed according to the problems exposed in the incident.

Key words: large generator, circuit breaker, start-up commissioning, short circuit fault