Analysis of Decoupling Loop Scheme for Tianjin Western Power Grid after Operation of 500 kV Xijiao Substation

LI Wenbo, YIN Chengzhu, YAN Fang, ZHAO Chenpeng, WANG Miao

Electric Power Construction ›› 2013, Vol. 34 ›› Issue (9) : 26-30.

PDF(702 KB)
PDF(702 KB)
Electric Power Construction ›› 2013, Vol. 34 ›› Issue (9) : 26-30. DOI: 10.3969/j.issn.1000-7229.2013.09.006

Analysis of Decoupling Loop Scheme for Tianjin Western Power Grid after Operation of 500 kV Xijiao Substation

  • LI Wenbo, YIN Chengzhu, YAN Fang, ZHAO Chenpeng, WANG Miao
Author information +
History +

Abstract

With strengthening of power grid, the short-circuit current has gradually become the factor restricting the development of power grid. Therefore, the effective solutions of short circuit become the priority during the development of regional power grid. At present, the western power grid in Tianjin is in operation with electromagnetic loop network. However, with the development of the power grid, especially the commissioning of 500 kV Xijiao substation, short-circuit problem of the 220 kV western power grid in Tianjin is becoming more and more prominent. The most effective measure to solve such issue is to decouple the 220 kV electromagnetic loop of the power grid. Based on the operation of Xijiao substation, two decoupling loop schemes were proposed for the 220 kV western power grid in Tianjin, one of which was recommended with detailed calculations and analysis of power flow, short-circuit current as well as transient stability of the power grid. Furthermore, suggestions for the future development of western power grid in Tianjin were provided.

Key words

western power grid in Tianjin / short-circuit current / decoupling loop scheme / power flow / stability

Cite this article

Download Citations
LI Wenbo, YIN Chengzhu, YAN Fang, ZHAO Chenpeng, WANG Miao. Analysis of Decoupling Loop Scheme for Tianjin Western Power Grid after Operation of 500 kV Xijiao Substation[J]. Electric Power Construction. 2013, 34(9): 26-30 https://doi.org/10.3969/j.issn.1000-7229.2013.09.006

References

 

[1]国核电力规划设计研究院.天津西郊(双青)500 kV输变电工程可行性研究报告[R].北京:国核电力规划设计研究院,2012.
[2]电力工业部电力规划设计总院.电力系统设计手册[M].北京:中国电力出版社,1998.
[3]Q/GWD 268—2009电网规划设计内容深度规定[S].北京:国家电网公司,2009.
[4]DL 755—2001电力系统安全稳定导则[S]. 北京:国家经济贸易委员会,2001.
[5]DL/T 5218—2005 220~500 kV变电所设计技术规程[S].北京:中国电力出版社,2005.
[6]张来,刘树勇,顾强,等. 2007年天津220 kV电网解环方案分析[J].华北电力技术,2007(5):40-42.
[7]李秋燕,姚峰,孙建华,等.河南电网2011年短路电流限制措施研究[J].电气应用,2012,31(9):30-33.
[8]白宏坤,李干生. 郑州220 kV电磁环网解环规划研究[J].电力系统保护与控制,2011,39(7):127-132.
[9]刘树勇,顾强,张丽娟,等. 天津电网中期运行方式研究[J].继电器,2008,36(5):28-31.