Control Strategy and Experimental Study of FCB in 660 MW Ultra-Supercritical Units

GUO Meng, HE Yagang, GU Yuchun, YU Ji’an, SU Qian

Electric Power Construction ›› 2014, Vol. 35 ›› Issue (9) : 97-102.

PDF(502 KB)
PDF(502 KB)
Electric Power Construction ›› 2014, Vol. 35 ›› Issue (9) : 97-102. DOI: 10.3969/j.issn.1000-7229.2014.09.018

Control Strategy and Experimental Study of FCB in 660 MW Ultra-Supercritical Units

  • GUO Meng1, HE Yagang1, GU Yuchun2, YU Ji’an2, SU Qian2
Author information +
History +

Abstract

The function of fast-cut back (FCB) is very important to maintain the stable of power grid and large thermal power plant. In the FCB test of 660 MW ultra-supercritical units in BuLian Power Plant, the normal combustion of boiler and the good furnace pressure could been maintained very well through the reasonable adjustment of coal mill trip order and intervals, as well as the coordination control of primary air, secondary air and induced air. The control method of HP and LP bypass, steam temperature and pressure, water level of condenser and deaerator were also discussed. The results show that the main parameters are fluctuated slightly and can be quickly stabilized. The rationality of control strategy and the integrity of logic function design are verified, which can provide references for the FCB test of ultra-supercritical units.

Key words

power and mechanical engineering / ultra supercritical / fastcut back (FCB) / control strategy

Cite this article

Download Citations
GUO Meng, HE Yagang, GU Yuchun, YU Ji’an, SU Qian. Control Strategy and Experimental Study of FCB in 660 MW Ultra-Supercritical Units[J]. Electric Power Construction. 2014, 35(9): 97-102 https://doi.org/10.3969/j.issn.1000-7229.2014.09.018

References

[1]冯伟忠.900 MW超临界机组FCB试验[J].中国电力,2005,38(2):74-77. [2]唐军,曲高君.伊朗ARAK电站4×325 MW机组的小岛运行经验[J].动力工程,2006,26(2):238-240. [3]张跃华,丁晓白,张鲁凡,等.河津电厂350 MW机组FCB性能试验分析[J].电力建设,2002,23(7):9-11. [4]冯伟忠.1 000 MW超超临界机组FCB试验[J].中国电力,2008,41(10):62-66. [5]冯伟忠.大机组实现快速甩负荷的现实性和技术分析[J].动力工程,2008,28(4):532-536. [6]陈浩.600 MW超临界机组FCB处理经验[J].热力发电,2006,35(6):62-64. [7]吴永存,朱介南.宁海电厂1 000 MW机组RB与FCB控制策略的设计和应用[J].电力建设,2011,21(1):59-63. [8]王学根,腾卫明,舒畅.通过控制系统改造实现国产600 MW超临界机组FCB功能[J].中国电力,2009,42(10):73-76. [9]郭萌.国电建投布连电厂一号机组FCB试验报告[R].西安:西北电力建设调试施工研究所,2013. [10]DL/T 711—1999 汽轮机调节控制系统试验导则[S]. [11]朱介南, 吴永存,罗韶辉,等.1 000 MW机组停机不停炉功能的设计和应用[J].中国电力,2010,43(8):18-21.