Steady-State Operation Parameters Calculation of Back-to-Back HVDC System
LI Peng, WEN Boying
Electric Power Construction ›› 2015, Vol. 36 ›› Issue (9) : 30-34.
PDF(649 KB)
PDF(649 KB)
Steady-State Operation Parameters Calculation of Back-to-Back HVDC System
The calculation of steady-state operation parameters plays an important role in the design process of back-to-back HVDC system. First of all, an explicit elaboration of the calculation model and control strategy used in the calculation of steady-state operation parameters was proposed, and then the calculation process was formulated based on these conditions. When HVDC system was operated in low power transmission, the operation parameters should be adjusted in order to engage converter in the balance control of reactive power between AC and DC systems. According to this problem, based on the discussion of the relationships among extinction angle and other steady-state operation parameters in back-to-back convertor station, an effective method of dichotomy iteration was put forward to solve the steady-state operation parameters that could meet the reactive power balance constraints during DC system low power operation. Finally, Gaoling back-to-back HVDC system was utilized to verify the correctness and effectiveness of this proposed algorithm. The result shows that this algorithm can be used in the packaged design of back-to-back HVDC system in the future.
back-to-back HVDC system / steady-state operation parameters / dichotomy / reactive power / control strategy
[1]赵婉君.高压直流输电工程技术[M].北京:中国电力出版社,2004.
[2]浙江大学直流输电科研组.直流输电[M].北京:水利水电出版社,1982.
[3]常浩,樊纪超.特高压直流输电系统成套设计及其国产化[J].电网技术,2006,30(16):1-5.
Chang Hao,Fan Jichao. System design and its localization of UHVDC transmission project[J]. Power System Technology,2006,30(16):1-5.
[4]梁旭明,张平,常勇.高压直流输电技术现状及发展前景[J].电网技术,2012,36(4):1-9.
Liang Xuming,Zhang Ping,Chang Yong. Recent advances in high-voltage direct-current power transmission and its developing potential[J]. Power System Technology,2012,36(4):1-9.
[5]张相宇,温渤婴,李鹏.高压直流输电系统主回路参数计算平台的研发[J].电力建设,2014,35(2):52-56.
Zhang Xiangyu,Wen Boying,Li Peng. Research and development of computing platform for main circuit parameters in HVDC power system[J]. Electric Power Construction,2014,35(2):52-56.
[6]段玉倩,饶宏,黎小林.高压直流输电系统主回路参数稳态特性计算方法[J].电力系统自动化,2007,31(16):53-56.
Duan Yuqian,Rao Hong,Li Xiaolin. Computational method of main circuit parameters of HVDC transmission systems[J]. Automation of Electric Power Systems,2007,31(16):53-56.
[7]王峰,徐政,黄莹,等.高压直流输电主回路稳态参数计算 [J].电工技术学报,2009,24 (5):135-140.
Wang Feng,Xu Zheng,Huang Ying,et al. Calculation of main circuit parameters for HVDC transmission[J]. Transactions of China Electrotechnical Society,2009,24 (5):135-140.
[8]刘宝宏,殷威扬,石岩,等.背靠背换流器控制策略的比较与分析[J].电网技术,2010,34(2):109-114.
Liu Baohong,Yin Weiyang,Shi Yan,et al. Comparison and analysis on control strategies for back to back converters[J]. Power System Technology,2010,34(2):109-114.
[9]邱伟,钟杰峰,伍文城.±800 kV云广直流换流站无功补偿与配置方案[J].电网技术,2010,34(6):93-97.
Qiu Wei,Zhong Jiefeng,Wu Wencheng. Reactive power compensation scheme and its configuration for converter station of ±800 kV DC power transmission project from Yunnan to Guangdong[J]. Power System Technology,2010,34(6):93-97.
[10]张啸虎,曹国云,陈陈.高压直流系统低功率运行时的无功控制策略[J]. 电网技术,2012,36 (1):118-122.
Zhang Xiaohu,Cao Guoyun,Chen Chen. Proposal on reactive power control of HVDC system during low power transmission[J]. Power System Technology,2012,36 (1):118-122.
[11]徐政.交直流电力系统动态行为分析[M].北京:机械工业出版社,2005.
[11]肖鸣,傅闯,梁志飞.高压直流低负荷无功优化功能运行分析 [J].电力系统自动化,2010,34(15):91-95.
Xiao Ming,Fu Chuang,Liang Zhifei. An operation analysis of HVDC low load reactive power optimization function[J]. Automation of Electric Power Systems,2010,34(15):91-95.
[13]谢开贵,吴韬,黄莹,等.基于二分法的高压直流输电系统可靠性最优分解[J].电工技术学报,2010,25(5):149-154.
Xie Kaigui,Wu Tao,Huang Ying,et al.Reliability optimal distribution for HVDC systems using bisection method[J]. Transactions of China Electrotechnical Society, 2010,25(5):149-154.
[14]杨万开,印永华,王明新,等.灵宝背靠背直流工程换流站和系统调试总结[J].电网技术,2006,30(19):36-41.
Yang KaiWan,Yin YongHua,Wang Mingxin,et al. Summary of converter station commissioning and system commission for Lingbao Back-to-Back HVDC project[J]. Power System Technology,2006,30(19):36-41.
/
| 〈 |
|
〉 |